PT. CAKRA PERKASA UTAMA (CPU) is Civil and Mechanical Electrical Construction Contractor Company, established on January 2016 in Jakarta.

PT. Cakra Perkasa Utama supported by good experience management and expertise who are reliable and experience more than 15 years in Electric Field, We committed to be a professional company and trusted who can give the best result successfully completed project for high client’s satisfaction.

We are specialist contractor on High Voltage Underground Cable (UGC) construction project. Our Expertise also take a variety high voltage 150kV project such as Substations and Transmissions.

Our commitment is to deliver a good quality service, on schedule and competitive price to ensure our client’s goals met.


PT. CAKRA PERKASA UTAMA (CPU) adalah perusahaan sipil dan electrical mechanical yang didirikan pada Januari 2016 di Jakarta.

Dengan didukung oleh pengalaman managemen dan tenaga ahli yang handal lebih dari 15 tahun di bidang kelistrikan, kami berkomitmen untuk menjadi perusahaan profesional yang dapat dipercaya dengan memberikan hasil terbaik agar dapat memberikan hasil yang terbaik untuk kepuasan bagi para klien kami.

Kami adalah kontraktor specialist untuk proyek Tegangan Tinggi Kabel Bawah Tanah. Kami juga dapat mengerjakan Tegangan Tinggi untuk Gardu Induk dan Transmisi.

Komitmen kami adalah memberikan quality yang terbaik, tepat waktu dan harga yang kompetitive untuk mencapai target dari klien kami.

OUR VISION


To be the best Underground Cable Contractor and High Voltage Contractor Leader in Indonesia.


OUR MISSION


To provide the best service and construction work to meet client’s goal.


OUR SERVICES



OUR CLIENTS & PARTNERS



OUR PROJECTS


No.Project NameDescriptionsOwnerContract
1SKTT 150kV Pelindo - Priok Barat, Location : JakartaInstall UGC 150kv, HDD, HDPE pipe installation, Pulling cable, Joint Bay, Fiber Optic - Grounding Installaton, Termination, and permit.PLN - PT. Rekadaya Electika 2016Subcontractor PT. Citra Gentari - PT. Cakra Perkasa Utama
2UGC 150kV Kebon Sirih - Gambir Lama, Location : JakartaInstall UGC 150kv, HDD, HDPE pipe installation, Pulling cable, Joint Bay, Fiber Optic - Grounding Installaton, Termination, and permit.PLN - nkt Cables 2016-2018 PT. Cakra Perkasa Utama
3Scattered Package 1: Supply and Install 17 Unit 500kV/150kv Transformer, Location : JakartaCivil work for 500kv TransformerPLN - Hyosung Corp. 2016Subcontractor PT. Alhas - PT. Cakra Perkasa Utama
4UGC 150kV Senayan - New Senayan, Location : JakartaInstall UGC 150kv, HDD, HDPE pipe installation, Pulling cable, Joint Bay, Fiber Optic - Grounding Installaton, Termination, and permit.PLN - nkt Cables, 2016-2018PT. Cakra Perkasa Utama
5UGC 150kV Semanggi Barat - Semanggi Timur, Location : JakartaInstall UGC 150kv, HDD, HDPE pipe installation, Pulling cable, Joint Bay, Fiber Optic - Grounding Installaton, Termination, and permit.PLN - nkt Cables 2016-2018 PT. Cakra Perkasa Utama
6Pembangunan EXT 2LB di GITET 500kV Bekasi (arah Gis Sumarecon)Civil dan Electromechano, Substation 150kV 2LBPLN - PT. Alhas Jaya Group, 2016PT. Cakra Perkasa Utama
7Scattered Package 2: UGC 150kV Gedung Pola - Manggarai, Location : JakartaInstall UGC 150kv, HDD, HDPE pipe installation, Pulling cable, Joint Bay, Fiber Optic - Grounding Installaton, Termination, and permit.PLN - Taihan Electric Wire Co., Ltd. 2016-2017Subcontractor PT. Citra Gentari - PT. Cakra Perkasa Utama
8Scattered Package 2: UGC 150kV Manggarai - Dukuh Atas, Location : JakartaInstall UGC 150kv, HDD, HDPE pipe installation, Pulling cable, Joint Bay, Fiber Optic - Grounding Installaton, Termination, and permit.PLN - Taihan Electric Wire Co., Ltd. 2016-2017Subcontractor PT. Citra Gentari - PT. Cakra Perkasa Utama
9Scattered Package 2: UGC 150kV, Mangga Besar - Ketapang , Location : JakartaInstall UGC 150kv, HDD, HDPE pipe installation, Pulling cable, Joint Bay, Fiber Optic - Grounding Installaton, Termination, and permit.PLN - Taihan Electric Wire Co., Ltd. 2016-2017Subcontractor PT. Citra Gentari - PT. Cakra Perkasa Utama
10Pembangunan SKTT 150kV GIS AGP - MAMPANGInstall UGC 150kV, Laying and Pulling Cable, Supply and Install Joint Bay, Steel Structure, HDD, Supply and Install Fiber Optic and GroundingPLN - KMI - PT. Rekadaya Electika, 2016PT. Cakra Perkasa Utama
11UGC 150kV ALAM SUTRA - CILEDUKInstall UGC 150kv, HDD, HDPE pipe installation, Pulling cable, Joint Bay, Fiber Optic - Grounding Installaton, Termination, and permit.PLN - KMI - PT. Rekadaya Electika, 2018PT. Cakra Perkasa Utama

OUR WORKS


CIVIL WORKS

ELECTRICAL MECHANICAL WORKS

UNDERGROUND CABLE 150kV WORKS

UNDERGROUND CABLE WORKS

Capacity of HDD is 30 Ton,
 40 Ton, 50 Ton and 100 Ton

EXCAVATION & OPEN TRENCH

HDPE PIPE INSTALLATION

HORIZONTAL DIRECTIONAL DRILLING (HDD)

CABLE MOBILIZATION

CABLE PULLING & LAYING

OUTER SHEATH TEST & PRECAST / CONVENTIONAL JOINT BAY

CABLE JOINTING & FIBER OPTIC INSTALLATION

TEST, COMMISIONING & RECOVERY

 